AIC CONTRACTING W.L.L | METHOD STATEMENT FOR ELECTRICAL, FIRE ALARM & ELV WORKS | MANATEQ PROJECT
PROJECT:
Supply, Installation, Testing & Commissioning of Electrical Works, Fire Alarm System & ELV Systems — MANATEQ Industrial Facilities, State of Qatar
CLIENT:
MANATEQ (Qatar Free Zones Authority)
CONTRACTOR:
AIC Contracting W.L.L
DOCUMENT TITLE:
Method Statement for Electrical Works, Fire Alarm & ELV Systems
DOC NUMBER:
AIC-MS-EL-01-R0
REVISION:
R0 — Issued for Approval
DATE:
June 2025
ISSUED BY:
AIC Contracting W.L.L — MEP Department

TABLE OF CONTENTS

S.NoContentsPage
11.0 Purpose
22.0 Scope of Works
33.0 Definitions & Abbreviations
44.0 Equipment Delivery, Storage & Handling
55.0 Precautions & Safety Program
66.0 References & Standards
77.0 Work Methodology
88.0 Activities — Step-by-Step Procedure
99.0 Documentation

1.0 PURPOSE

The purpose of this Method Statement is to establish a systematic, safe, and compliant procedure for the execution of all Electrical Works, Fire Alarm System, and ELV (Extra Low Voltage) works associated with the MANATEQ Industrial Facilities Project in the State of Qatar.

This document ensures that all electrical and ELV activities are performed in accordance with KAHRAMAA regulations, QCDD requirements, Qatar Construction Specifications (QCS), IEC/NFPA standards, and industry best practices, while maintaining personnel safety, asset protection, and regulatory compliance as the highest priorities.

2.0 SCOPE OF WORKS

2.1 Electrical Works

2.2 Fire Alarm System

2.3 ELV / Structured Cabling

2.4 Exclusions

3.0 DEFINITIONS & ABBREVIATIONS

AbbreviationDescription
MS / PTW / LOTOMethod Statement / Permit to Work / Lockout-Tagout
FACP / FARPFire Alarm Control Panel / Repeater Panel
XLPE / SWA / PVCCross-linked Polyethylene / Steel Wire Armoured / Polyvinyl Chloride
MCCB / MCB / ATSMoulded Case Circuit Breaker / Miniature CB / Automatic Transfer Switch
DOL / MCCDirect On-Line starter / Motor Control Centre
QCS / QCDD / KAHRAMAAQatar Construction Specifications / Civil Defence / Qatar General Electricity & Water Corp.
ELV / CAT6 / GIExtra Low Voltage / Category 6 / Galvanised Iron
IEC / NFPAInternational Electrotechnical Commission / National Fire Protection Association

4.0 EQUIPMENT DELIVERY, STORAGE & HANDLING

Delivery: All equipment delivered with packing lists and certificates. 48h notice to client. Damaged items rejected.

Storage: Indoor: panels, MCCs, FACP stored in clean dry area ≤85% RH. Cables on wooden pallets covered, drums upright. Fire alarm devices stored in secure, dry store.

Handling: Mechanical lifting for heavy items (forklifts, cranes); cable drums rolled correctly; anti-static for electronic components; lifting gear certified (5:1 safety factor).

5.0 PRECAUTIONS & SAFETY PROGRAM

5.1 General Safety Precautions

HazardControl Measure
Electric Shock / Arc Flash100% LOTO, voltage verification before work, arc flash PPE (face shield, rubber insulating gloves).
Fire HazardCO2 extinguisher within 5m, hot work permit, fire watch 30 min after activity.
Manual HandlingTeam lifting (>50kg), cable rollers, mechanical aids for heavy panels.
Working at HeightScaffold certificate, full body harness >1.8m, guardrails and toe-boards.
Confined SpaceGas monitoring, ventilation, standby attendant, rescue plan.

Safety Program: PTW displayed at work location; LOTO personal locks; all personnel inducted; PPE mandatory (helmet, hi-vis, safety shoes, arc flash for live panels). RAMS briefed to operatives. Emergency numbers posted. Housekeeping daily.

6.0 REFERENCES & STANDARDS

7.0 WORK METHODOLOGY

8.0 ACTIVITIES — STEP-BY-STEP PROCEDURE

8.1 Site Preparation & Safety Setup

StepActionResponsibility
1Obtain PTW & isolation permit from MANATEQ engineering.Project Engineer
2Apply LOTO, verify zero energy with calibrated tester.Electrical Supervisor
3Identify cable routes & equipment positions per SLD.Supervisor
4Erect barricades, signage & position fire extinguishers.HSE Officer

8.2 LV Switchgear & Cable Installation

StepActionResponsible
1Unpack/inspect LV panels, SMSBs, MCCs against submittals.Project Engineer
2Mount panels on prepared plinths, fix ATS & DBs.Electrician
3Pull XLPE/PVC cables (35–400mm²) via trays and conduits, maintain bending radius.Electrician
4Terminate cables with SWA glands, torque per spec, ensure earth continuity.Electrician

8.3 Fire Alarm System Installation (Summary)

StepActivityResponsible
1Mount FACP in Industrial Building (G), Repeater panel in Guard Room.Fire Alarm Engineer
2Install steel back-boxes, pull fire-resistant cables, install detectors (smoke/heat/beam), MCPs, sounders/flashers.Fire Alarm Tech
3Terminate modules, install EOL resistors, emergency lights & exit signs.Electrician
4Program FACP, cause-and-effect, simulate alarm conditions, perform QCDD walkthrough test.Fire Alarm Engineer

8.4 ELV Structured Cabling

Install UPVC conduits & junction boxes, pull CAT6/fibre cables, terminate RJ45 outlets (38 No.), perform Fluke certification per TIA/EIA 568-C.2.

8.5 Testing & Commissioning (Selected tests)

Test RefTest DescriptionAcceptance Criteria
IR TestInsulation resistance 500V/1000V megger≥1 MΩ (typical >100 MΩ)
Earth ContinuityContinuity of protective conductors<1 Ω
ATS ChangeoverSimulate mains failureGenerator auto-start and transfer within specified time
Smoke DetectorAerosol/heat bar testFACP indicates correct zone/address
Beam DetectorAlignment & obscuration testAlarm within sensitivity range
Battery Backup (FACP)24h standby + 30min alarmSystem fully operational per QCDD
CAT6 LinkFluke DSX or equivalentPass: NEXT, return loss, propagation delay

8.6 Energisation & Load Testing

9.0 DOCUMENTATION

Work Inspection Requests (WIR): submitted at tray installation, cable pulling, panel installation, device mounting, pre-commissioning hold points.

Test Reports: IR, earth continuity, fire alarm commissioning (detector test, battery test, loop resistance), generator load test, ATS report, CAT6 certification.

As-Built Drawings: electrical distribution, fire alarm, ELV/data – submitted within agreed timeframe.

O&M Manuals: LV panels, MCCs, FACP, generator, ATS, structured cabling.

Completion Certificate: submitted after satisfactory commissioning and client acceptance.


— END OF DOCUMENT — AIC-MS-EL-01-R0 —

Prepared by AIC Contracting W.L.L | MEP Department | Approved for issue